New Lynn War Memorial Library
Villa Maria Winery Upgrade
Portland Tower
 

Project:  Villa Maria Winery Upgrade

Date:  February 2006

Location:  Auckland

Architect:  Archimedia Ltd

Engineer:  Harrison Grierson Consultants

Contractor:  Argon Construction

Concrete Supplier:  W Stevenson & Sons Ltd

Type of Unit:  Large number of structural and decorative walls of different sizes, configurations and off-form finishes.

Reason for choosing SCC:  SCC was suggested by the concrete supplier and accepted by the architect and engineer to provide a high quality architectural finish.

Outcome:  The off-the-form finish quality achieved and exceeded the specified parameters.  The lack of vibrators, electrical cables and access platforms on site improved the working environment, which was recognised and appreciated by the construction team.  Although construction savings were not measured, the speed of concreting and reduction in labour costs increased productivity.

Submitted by:  Michael Khrapko, W Stevenson & Sons